Implementation of underground and surface drainage of Raad Farm

PROJECT

Implementation of underground & surface drainage of Raad land

CLIENT

Khuzestan Agricultural Company...

STATUS

Completed

Project Duration

Raad ( 12 month)



Project specification:

Raad drainage consists of about  2500 ha of  some part of this land which including about 354 drainage to improve the structure of the Earth.

Laterals:

600
kilometer pipe laying  of PVC pipe in sizes  of 125 and 200 mm

Collector: 50 km

Manhole
: 1008 manhole

Deepening and widening of open
canals:4.5 km